Apex Trader Funding - News
BQE Water Reports Q1 2024 Results
VANCOUVER, BC, May 29, 2024 /CNW/ - BQE Water Inc. (TSXV:BQE), a leader in the treatment and management of mine impacted waters, is pleased to release its interim consolidated financial results for the three months ended March 31, 2024.
"In Q1 2024, we doubled our recurring operation revenues over the same period last year as our new streams of recurring revenue in the US mitigated the seasonality of our existing operations," said David Kratochvil, President & CEO of BQE Water. "Growing such revenue streams remains a strategic priority for us as we expand recurring revenues through additional plant operations over time. While our technical services for Q1 2024 decreased when compared to Q1 2023, we expect it to catch up to 2023 levels over the remainder of the year."
FINANCIAL HIGHLIGHTS
Recorded Proportional and GAAP revenues of $3.4 million and $2.5 million in Q1 2024 respectively, compared $3.6 million and $2.7 million in Q1 2023.
Doubled recurring plant operation revenues to $1.8 million in Q1 2024 when compared to Q1 2023.
Gross margin of $1.1 million in Q1 2024 compared to $1.0 million in Q1 2023, an 11% increase.
Net loss of $486,000 in Q1 2024 compared to a loss of $342,000 in Q1 2023.
Adjusted EBITDA loss of $121,000 in Q1 2024 compared to a loss of $80,000 in Q1 2023.
Net cash and cash equivalents of $8.2 million at March 31, 2024, compared to $7.9 million at December 31, 2023, a 4% increase.
Working capital of $9.9 million at March 31, 2024, compared to $10.5 million at December 31, 2023, a 6% decrease.
Selected financial results are as follows:
(in '000s)
3 months ended Mar. 31
2024
2023
Revenue from Operation Services
1,789
835
Revenue from Technical Services
719
1,856
Revenue from joint ventures in China
902
869
Proportional Revenues
3,410
3,560
OPERATIONAL SERVICES HIGHLIGHTS
Our operational services consist of the operation or technical supervision of water treatment plants, which generate recurring revenues from three main sources: sales of recovered metals, water treatment fees and operations support fees. The Company's operations by source of revenue are as follows:
Operations
Location
Revenue Source
JCC-BQE Joint Venture
Jiangxi province, China
Sales of recovered metals
MWT-BQE Joint Venture
Shandong province, China
Sales of recovered metals
Raglan Mine for Glencore
Northern Québec, Canada
Water treatment fees
Minto Mine for Government of Yukon
Yukon, Canada
Water treatment fees
Zhongkuang Metallurgical Facilities for MWT
Shandong province, China
Operations support fees
Zhaojin Metallurgical Facilities for MWT
Shandong province, China
Operations support fees
Power utility ash pond for WesTech
Eastern USA
Water treatment fees
Base metal project for a metal producer
Southwestern USA
Water treatment fees
JCC-BQE Joint Venture Operations
Our 50/50 joint venture with partner Jiangxi Copper Company ("JCC") operates three water treatment plants at Dexing Mine and at Yinshan Mine in Jiangxi province of China. The volume of water treated and pounds of copper recovered by the plants fluctuate seasonally depending on precipitation levels in the region. The operating results for Q1 2024 are as follows:
(in '000s)
3 months ended Mar. 31
2024
2023
Water treated (cubic metres)
4,217
2,899
Copper recovered (pounds)
380
291
In Q1 2024, all three plants met mechanical availability and process performance targets set by the Company. The volume of water treated increased by 45% and the mass of copper recovered increased by 31% compared to Q1 2023. Such changes in water volume and feed grade from period to period are largely the result of environmental conditions beyond the control of the joint venture.
MWT-BQE Joint Venture Operations
Our 20% share in MWT-BQE is with our 80% partner Beijing MWT Water Treatment Project Limited Company ("MWT") and together we operate a water treatment plant at a smelter in Shandong province of China. MWT-BQE generates revenues from the sale of zinc and copper recovered from smelter wastewater. Operating results for Q1 2024 are as follows:
(in '000s)
3 months ended Mar. 31
2024
2023
Zinc recovered (pounds)
31
78
Copper recovered (pounds)
5
41
The smelter periodically operated its production lines with ores from different sources which led to varying concentrations of zinc and copper in the feed and a fluctuation in the volume of wastewater treated by the plant. The joint venture has no control over the composition and volume of feed that flows into the plant.
BQE Water ...